This article is the fourth in a series dealing with some of the basic “hows” of the Maintenance profession.
A storeroom is, by definition, a waste of capital. It is a bucket of money set aside for contingencies associated with the unpredictable nature of the manufacturing process.
In a perfect world, storerooms would not even be necessary. Your world-class preventive maintenance efforts would ensure that machinery seldom wore out. Parts would arrive from suppliers 10 minutes before they were scheduled for replacement based on recommendations from the predictive maintenance side of the house. Since there would be no emergencies, the need for a selection of replacement components to be kept on site would be eliminated.
In the real world, production facilities don’t operate in ideal settings; some level of spare parts availability must be maintained. Each maintenance organization must determine the minimum number of extra components necessary to sustain production and then strive to reduce excess supply with a minimum of waste.
Changing the scenario
Sometimes, storerooms seem to be stocked with the philosophy that the plant should be completely rebuildable from parts on hand. That philosophy might have merit if holding costs associated with the yearly maintenance of parts inventories did not range from 18 to 30% of the inventory’s value. On a million-dollar storeroom inventory, this translates into between $180,000 and $300,000 per year. As a result, the cost of your parts supply doubles every three to five years.
Pretty shocking, isn’t it. This is real money, too—not just an on-paper figure that the accounting department has circulated. The components of this expense include the opportunity cost of not spending the money on something else, interest, the cost of the storage facility, handling, spoilage, taxes, employees and loss.
If this picture describes your maintenance stores reality and you wish to change the scenario, you must first determine the scope of the problem. Your CMMS will be one of your most useful tools as you undertake this task, because it will allow you to identify slow-moving and non-moving inventory, overstocks and components that have become obsolete due to a change in your process. Once these superfluous parts have been identified, a systematic program of reduction and elimination must be undertaken.
Each maintenance manager must look at the available personnel in the department and assign a single person to spearhead the campaign to reduce surplus stores. The planner or storeroom coordinator would be excellent candidates for this role if some of their current duties could be shifted to free up the hour or two per day—every day—that this project will require. The designated individual should then be assigned the task of reducing inventory via the following methodology:
As an example, if you have a bearing come up for reorder because one was issued the previous day, several factors must be considered before the requisition is transmitted to your supplier. How many identical bearings are still in stock? Has a cross-reference been run to determine if any other in-stock bearings will work in the application? When was the last time one of these bearings failed? Why did this one fail? Was the issued part actually used? What is the delivery time on a new bearing? What is the criticality of the affected machine? If you normally stock two of these bearings, but you have only used one in the last three years, and the re-order time is two days, then most likely you do not need to re-order this component at present. If it turns out that temporary loss of the machine’s functionality will not cause an interruption in production, then you do not need to reorder next time, either.
It is very important to remember that reorder points and stocking levels must be formally changed in your CMMS or stores program if you decide that you can operate your process with lower levels of spares. Otherwise, the orders will just keep on coming.
Getting it done
Keep in mind that your storeroom inventory level did not get where it is overnight. It climbed slowly but steadily over time. Consequently, its reduction also must proceed at a measured pace—if you want to avoid unnecessary waste while eliminating undesirable surplus materials.
One of the key elements in painless storeroom inventory reduction is to have one person responsible for the process, and to have that individual work at the project on a daily basis. Even if he/she can spare only an hour per day for the task of inventory reduction, the time will be well spent. TF
Ray Atkins, CPMM, CMRP, is a veteran maintenance professional with 14 years experience in the lumber industry. He is based in Rome, GA, where he spent the last five years as maintenance superintendent at Temple-Inland’s Rome Lumber facility. He can be reached at This e-mail address is being protected from spambots. You need JavaScript enabled to view it
WIRELESS TEST TOOLS CAN CUT TROUBLESHOOTING TIMEBy: Fluke Corporation
The automation of more and more processes and operations in today’s factories and commercial buildings is helping to reduce energy consumption and increase safety and productivity as never before. However, automation has also added a large dose ofcomplexity for the technicians who maintain and troubleshoot the systems. Click here to learn how Fluke's CNX 3000 Wireless system can help.

New Pig’s PIG® Latching Drum Lids enable quick, easy drum access and secure closure to help meet closed container regulations. Designed to open and close easily with one hand, the Lids keep drum contents dry and pure without hassle.
A partnership with Maintenance Technology and Lubrication Management & Technology keeps your message, products and services in front of 82,000+ decision-makers 24/7/365.
Online, in print and in person, our two synergistic publications are better than one. For more information, click here to contact your MT/LMT Sales Representative today.