We know there are two principal inputs to the maintenance cost equation: Reduce or eliminate the need to do maintenance (reliability of equipment), and improve the effectiveness of the resources needed to accomplish maintenance (people, parts, and outside services).
Leadership and crafts both want greater productivity in the execution of work. Leadership definitely wants to reduce waste and the dollars associated with it. Crafts want to utilize their time and skills effectively to accomplish equipment tasks professionally. Eliminating wasted time is good for business and good for general morale.
Typical wrench time ranges from 25 to 35 percent while benchmark levels range from 50 to 60 percent. What time-wasting issues make up this gap? From past Viewpoint articles you know that I see things through Six Sigma glasses. Using Six Sigma methodology, we can discover the set of circumstances that represent the gaps. Fundamental to Six Sigma thinking is that: Y (wrench time) = f (x1, x2, x3, x4, &).
What are some of the xs? How about stores delays, equipment preparation, work permitting, travel time, incomplete or wrong diagnosis, inadequate tools, waiting on the cherry picker, bad or wrong spare parts, inadequate work plans, and more.
The trained Black Belt or Green Belt will summon the disciplined Six Sigma roadmap: Measure
Analyze
Improve
Control (MAIC). A team of cross-functional stakeholders will drive the effort to eliminate these daunting wastes. Some key MAIC tools include:
Of the bullets above, measuring becomes a key element of the effort to improve. How is the current process performing? Where are the wastes? How often do these wastes occur (frequency, or MTBF)? How severe are the waste events (time wasted, or MTTR)?
To answer these questions, a data collection method needs to be designed and deployed. Work sampling is one method. Another approach is to "follow the babies," as we say in Six Sigma; maintenance events (work orders) are literally followed from start to finish. It sounds simple, almost juvenile; but the team will be amazed by what it learns about how the current process works and what comprises the defects (wastes).
Once the measuring phase has been completed, a cadre of immediate quick fixes and opportunities (greater analysis required) will emerge. The opportunities likely will point to broken supporting processes (job plans, work permits, tool crib, outside services coordination).
None of these are simple processes with easy fixes. They likely will require a new, more detailed set of work-process improvement projects.
One of the truisms of Six Sigma is "you don't know what you don't know." Once you have data (now you know), it becomes very apparent that the interactions of maintenance activities are quite complex. If your wrench time is estimated in the 35 percent range, then your maintenance work process is broken.
What supporting processes are broken? You know that the brokenness is impacting the margin on the products you produce, and therefore can be classified a business driver for your company.
Go find out by measuring and converting to estimated dollars wasted (cost of poor quality in Six Sigma terminology). Then begin a structured MAIC path to uncover the defects, mitigate the failure modes, and install the should-be processes to control and sustain to benchmark wrench time. MT
WIRELESS TEST TOOLS CAN CUT TROUBLESHOOTING TIMEBy: Fluke Corporation
The automation of more and more processes and operations in today’s factories and commercial buildings is helping to reduce energy consumption and increase safety and productivity as never before. However, automation has also added a large dose ofcomplexity for the technicians who maintain and troubleshoot the systems. Click here to learn how Fluke's CNX 3000 Wireless system can help.

New Pig’s PIG® Latching Drum Lids enable quick, easy drum access and secure closure to help meet closed container regulations. Designed to open and close easily with one hand, the Lids keep drum contents dry and pure without hassle.
Are you struggling with a high ratio of emergency (unplanned) to planned work orders, a huge backlog, a lack of sufficient resources, an inability to balance the work load, constant work interruptions, not having parts when needed, recurring failures, and much more. In these lean times, when more is expected from fewer resources, having a highly efficient maintenance program with thoughtful planning and scheduling is the key to success.
This white paper will help you reduce maintenance costs and maximize efficiency. Click here to download the White Paper.