Over the past several years, managers up through the CEO have come to recognize equipment uptime as a key part of any successful operating strategy. Equipment availability is one of the key performance indicators of a maintenance organization. Goals are set based on “gut feel,” or by benchmarking with similar facilities within the organization or with similar organizations within the same industry.
Both these goal-setting methods involve high levels of uncertainty that can lead to overspending for maintenance and overtaxing of maintenance resources. The uncertainty of “gut feel” speaks for itself. Benchmarking involves high levels of uncertainty due to the difficulties created by not knowing the exact guidelines each facility uses for recording unavailability.
Here is a framework for managing availability goals to help meet the financial goals of an organization. We will examine availability in detail: the three types of availability and how they relate to each other, the factors that determine availability, and recommendations for improving the setting of goals.
Availability types
The three subtypes of availability are inherent, achievable, and operational (see Fig. 1). Each subtype has specific characteristics determined by:
It is important to understand the distinctions among the three subtypes in order to design, measure, and manage integrated subgoals:
These factors have the following strategic implications:
The conclusion from these factors is that eventually Aa must be known. Otherwise, many of the current goals to develop world-class maintenance operations are not possible. It is the organization that makes the most money—not the one with the highest availability—that wins the game.
Determining availability
Availability is a function of reliability and maintainability—in other words, how often equipment will fail and how long it takes to get the equipment back to full production capability. Reliability, maintainability, and therefore, availability, are determined by the interaction of the design, production, and maintenance functions (see accompanying section “Top- Level Factors That Affect Availability”).
The implication is that availability is largely determined by how well designers, operators, and maintainers work together.
Optimizing availability
Profitable plant availability is the result of optimizing Ai, Aa, and Ao. Because no plant can achieve availability higher than Aa, achievable availability is the first to be optimized (see Fig. 2).
All equipment fails based on its design even when operated and maintained perfectly. Every maintenance activity, whether scheduled or unscheduled, is representative of an equipment failure. Scheduled or time-based maintenance seeks to correct failures before they can affect equipment performance. Unscheduled maintenance is corrective maintenance performed as the result of breakdown or the detection of incipient failure.
Achievable availability is the result of several factors:
The cost curve represents strategic decisions to invest large amounts of capital up front to increase Aa through hard design, or to spend operating dollars to increase Aa through more intensive maintenance strategies. These decisions are driven by many factors, such as the need to get a product to market quickly, the availability of capital, and the operating mentality of the company.
Availability and costs
The availability/cost curve relationship highlights the fact that availability is a proxy of revenues. At some point of either extreme of the cost curve or the availability curve, the cost of availability will exceed the income it allows. Without availability management, operating beyond those intersections can occur without management’s awareness; normal accounting practices and other maintenance performance indicators cannot easily reveal this practice.
The difference between achievable and operational availability is the inclusion of maintenance support. Achievable availability assumes that resources are 100 percent available and no administrative delays occur in their application. Therefore, maximum operational availability theoretically goes to achievable availability. In reality, every human endeavor has a natural upper limit of obtainable perfection that prevents Ao from reaching Aa.
The shape and location of the operational availability curve are determined by the level of maintenance operation resources and organizational effectiveness. Resources and organizational effectiveness have upper bounds above which additional spending will not yield better results. At that point, achievable availability must be increased to give Ao room to move upward. Aa can be increased by new maintenance strategies, provided that the plant is not operating at the peak of the Aa curve. Capital investment is required to move the Aa curve upward if the plant is operating on the peak.
This is important. Without availability engineering and management, it is easy to unknowingly spend beyond the point of maximum return. This may occur when plant performance falls short of management’s desired productive capacity. Management tries to achieve gains with increased stress on maintenance support. However, the operational availability curve has already been unknowingly forced against the achievable availability curve. The result is throwing good money after bad. Spending is in the loss zone to the right of the intersection of the achievable availability and cost curves.
Determining achievable availability for an existing facility
Few physical asset managers have had the luxury of being an integral part of the design phase of their physical plant. Therefore, they need to analyze the current physical plant to determine its achievable availability.
Determining achievable availability is a four-step process:
1. Build a reliability block diagram (RBD) of the plant’s critical systems. Use publicly available reliability data for failures. Using plant data skews the results based on plant organizational effectiveness. Use plant data or works estimation techniques to determine mean time to repair. Again, using plant data skews the results based on plant organizational effectiveness.
2. Determine logistical delays created by plant hard design: to/from shops, to/from stores, accessing equipment.
3. Add in scheduled maintenance downtime for the chosen preventive maintenance strategy.
4. Perform availability simulations.
The scope of the analysis is determined by resources, time, and the desired quality of the result.
Building the RBD
The RBD is a graphical representation of the plant systems, subsystems, and components arranged in a way that reflects equipment interdependence (see Fig. 3). The RBD is the cornerstone of the availability model because it shows how failure in a plant element affects process uptime.
It is important to note the reliability implications of the systems presented in Fig. 3. Serial systems are inherently unreliable. The failure of a single element in the system results in a stoppage of the overall system. Fully redundant parallel systems are inherently reliable. The system stops only if all the redundant systems fail at the same time. Redundancy is an important tool in improving overall system reliability. See Practical Machinery Management for Process Plants, Volume 1, 3rd Edition: Improving Machinery Reliability by Heinz P. Bloch for a more complete discussion.
All complex machines are built from the same few basic machine elements of couplings, bearings, gears, motors, belts, and so on. The RBD is refined by breaking down the top-level RBD into several RBDs that represent each top-level system (see Fig. 4).
Obtaining failure and repair data
After the RBDs are built, failure and repair data must be obtained for use in availability simulations. Obtaining this data is a time-consuming task. The desired degree of certainty dictates the level of effort required for this stage of building the model. It is important to remember that this is not an exact science. Perfection is not required. You need only be better than your toughest competition
There are many sources for failure data. This is not an exhaustive list:
Reliability Analysis Center—Electronic parts reliability data (EPRD), non-electronic parts reliability data (NPRD). Available in print and software versions.
Paul Barringer’s Web site—Weibull data for many components plus links to other available data and reliability web sites.
Practical Machinery Management for Process Plants, Volume 1, 3rd Edition: Improving Machinery Reliability, Heinz P. Bloch, Gulf Professional Publishing, ISBN: 087201455X—Table of equipment failure data plus practical information on improving equipment and system reliability.
Plant data—Failure data depends on the robustness of the data-collection system. Using plant data skews the analysis by including plant organizational effectiveness.
Binomial and Weibull distributions typically are used to present failure data for modeling purposes. Most availability simulators accept either type of data.
Obtaining repair data is a much more difficult task. Repair data is typically not available anywhere in tabular form. Repair times are very dependent on the configuration of the equipment and the plant. Equipment with a great deal of guarding and with parts located in tight spots requires much longer repair times than equipment with little guarding and plenty of space in which to work. The two primary methods of obtaining repair time data are analyzing current plant data and using works estimation systems such as MOST to estimate times (see accompanying section “Obtaining Repair Time Data”). Each method has its own set of difficulties.
In the next installment of this article, we will discuss using the availability model to determine plant bottlenecks and increase throughput, the impact of the need for modeling and analysis on the maintenance and engineering organization, and offer suggestions on how to close the natural gaps between the three types of availability. MT
This e-mail address is being protected from spambots. You need JavaScript enabled to view it is president of ARMS Reliability Engineers-USA, LLC, 8450 N. Devonshire Woods Pl., West Terre Haute, IN 47885; (812) 535-1445

Fig. 1. It is important to understand the distinctions among the three subtypes in order to design, measure, and manage integrated subgoals.

Fig. 2. Because no plant can achieve availability higher than achievable availability, Aa, it is the first to be optimized.

Fig. 3. The RBD is the cornerstone of the availability model because it shows how failure in a plant element affects process uptime.

Fig. 4. Breaking down the top-level RBD shows several RBDs that represent each top-level system.
back to article
TOP-LEVEL FACTORS THAT AFFECT AVAILABILITY
|
Reliability
|
Maintainability
|
|
Reliability Factors Driven by Design
|
Maintainability Factors Driven by Design
|
|
Factors Driven by Maintenance Decisions |
|
|
|
|
Factors Driven by Operations Decisions |
|
|
|
|
(Source: Availability Engineering and Management, Richard G. Lamb, Prentice Hall; ISBN: 0133241122) |
|
|
Method |
Advantages |
Limitations |
|
Analyzing plant data |
|
|
|
Works estimation system |
|
|